Drill cuttings area measuring 167 x 129 m
During the construction of the “drill cuttings site”, 8302 m3 of concrete was poured
Drainage channel around the perimeter of concrete paving.
Channels for laying lines for technological needs and laying cables.

Installation of a reinforced concrete slab measuring 51 x 70 x 0.3 m, for the subsequent placement of equipment for processing, disposal of sludge and related structures necessary during operation
Concrete paving with a thickness of 250 mm for the passage of equipment around the sludge tanks.